Construction Progress of the new House

ActivityDate
Lot clearing 1 10/13/2001
Lot clearing 2 10/20/2001
Septic System and Footing Dug out 10/27/2001
Foundation 11/03/2001
1st Floor Framing 11/10/2001
Completed Framing, Power, 2nd Floor Ducting 11/17/2001
Plumbing, Electrical, Water 11/22/2001
Complete Brick, start siding, phone/cable 12/01/2001
Complete siding, inside drywall 12/09/2001
Deck/Vinyl Floors 12/16/2001
Cabinets/Painted/Driveway 12/23/2001
Painted/Plumbing Fictures 12/30/2001